Project Acceleration Analysis Using the Crashing Method With The Addition of Four Hours of Work and The Shift Work System Case Study : RSUB Malang Building Construction Project
DOI:
https://doi.org/10.30649/japk.v11i1.61Keywords:
Project Acceleration, Crashing Method, Direct Cost, Indirect CostAbstract
In the process of building a construction project, work delays often occur on the project. So we need an alternative that can be used to support the acceleration of project completion. In this study, we will analyze the acceleration of duration in the construction project of RSUB Malang Building, with the alternative of adding four hours of work and the work shift system (morning shift and night shift). The total project cost budget in post-crashing conditions with the alternative of additional working hours was Rp.12,312,448,567.00 or more expensive 0.82% of the total project cost budget under normal conditions and the duration of project implementation was 191 working days or faster 9, 05% of the normal duration, while the total project budget in conditions after crashing with an alternative work shift system was Rp. 12,155,175,517.00 or 0.47% cheaper than the total project cost budget under normal conditions and the duration of project implementation was 179 days or 14.76% faster than the normal duration. It can be concluded that implementing a work shift system is a more effective and economical alternative to crashing, because the duration is faster and the total project cost budget is cheaper.
References
Anggraeni. (2016). Analisis Percepatan Proyek Menggunakan Metode Crashing dengan Penambahan Tenaga Kerja dan Shift Kerja. Tugas Akhir. (Tidak diterbitkan), Universitas Sebelas Maret.
Azzam. (2016). Analisis Percepatan Proyek Pembangunan Java Village Resort Dengan Menambahkan Tenaga Kerja dan Jam Kerja. Tugas Akhir. (Tidak diterbitkan), Universitas Islam Indonesia.
Budiono. (2006). Simulasi Waktu dan Biaya Pada Konstruksi PIER Pada Jalan Layang Suprapto Jakarta. Jakarta : Universitas Indonesia.
Ervianto. (2002). Manajemen Proyek Konstruksi, Edisi Pertama. Yogyakarta : Salemba Empat.
Ervianto. (2003). Manajemen Proyek Konstruksi, Edisi Revisi. Yogyakarta : Andi.
Ervianto. (2004). Teori Aplikasi Manajemen Proyek Konstruksi. Yogyakarta : Salemba Empat.
Ervianto. (2005). Manajemen Proyek Konstruksi, Edisi Revisi. Yogyakarta : Andi.
Frederika. (2010). Analisis Percepatan Pelaksanaan dengan Menambah Jam Kerja Optimum pada Proyek Konstruksi (Studi Kasus : Proyek Pembangunan Super Villa, Peti Tenget-Bandung), (Journal Online). (Tidak diterbitkan, http://www.scribd.com/document/205836025/Jurnal-Analisis-PercepatanPelaksanaan-Dengan-Menambah-Jam-Kerja-Optimum-Pada-ProyekKonstruksi, diakses pada 20 Desember 2020.
Hanna. (2008). Impact Of Shift Work On Labor Productivity For Labor Intensive Contractor. Journal Of Construction Engineering And Management.
Husen. (2009). Manajemen Proyek : Perencanaan, Penjadwalan, dan Pengandalian Proyek. Yogyakarta : Andi.
Husen. (2010). Manajemen Proyek. Yogyakarta : Andi.
Iramutyn. (2010). Optimasi Waktu Dan Biaya Dengan Metode Crash. Tugas Akhir. (Tidak diterbitkan), Universitas Sebelas Maret.
Kerzner, (2000). Project Management A System Approach to Planning, Schedulling and Controlling. Singapore.
Keputusan Menteri Tenaga Kerja No. KEP-102/MEN/VI/2004 Tentang Waktu Kerja Lembur dan Upah Kerja Lembur (online). (Tidak diterbitkan), https://www.scribd.com/doc/131149015/KEPMEN-102-MEN-VI-2004 diakses pada 20 Desember 2020.
Ningrum. (2016). Penerapan Metode Crashing dalam Percepatan Durasi Proyek Dengan Alternatif Penambahan Jam Lembur Dan Shift Kerja. Tugas Akhir. (Tidak diterbitkan), Universitas Sebelas Maret.
Peraturan Presiden Nomor 70 Tahun 2012 Tentang Pengadaan Barang dan Jasa (online). (Tidak diterbitkan), http://www.peraturan.go.id/perpres/nomor-70-tahun-2012-11e44c4f4ea07e708ca1313232303233.html diakses pada 20 Desember 2020.
Soeharto. (1997). Manajemen Proyek Dari Konseptual Sampai Operasional. Jakarta: Erlangga.
Soeharto. (1999). Manajemen Proyek Dari Konseptual Sampai Operasional Jilid 1. Jakarta : Erlangga.
Soeharto. (1999). Manajemen Proyek Dari Konseptual Sampai Operasional Jilid 2. Jakarta : Erlangga.
Sutisna. (2013). Pengaruh Percepatan Waktu Pelaksanaan Terhadap Biaya Pada Pekerjaan Struktur Bawah Jembatan di Kabupaten Buatan, Pekanbaru, Riau. Tugas Akhir. (Tidak diterbitkan), Universitas Indonesia.
UU RI No. 25 Tahun 1997 Tentang Ketenagakerjaan (online). (Tidak diterbitkan), http://www.hukumonline.com/pusatdata/downloadfile/lt4ec12f260b0ab/parent/734, diakses pada 20 Desember 2020.
Yana. (2009). Pengaruh Jam Kerja Lembur Terhadap Biaya Percepatan Proyek Dengan Time Cost Trade Off Analysis. Tugas Akhir. (Tidak diterbitkan), Universitas Udayana Bali.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2020 Ahmad Ridwan

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.